Materials shortage prompts extra planning
Contents |
[edit] Introduction
Increasingly long lead times for many products in mid-2021 has prompted ECA and SELECT to alert their members to the extended delays and urge them to plan ahead and order early. SELECT is the trade association for the electrical contracting industry in Scotland.
The joint call comes after ECA and SELECT met to identify key strategies and discuss how to continue their close collaboration. The two electrical trade bodies examined skills, training and the green revolution during the virtual meeting as they debated priorities for the second half of 2021 and beyond
[edit] Extended shortages anticipated
The warning by the trade associations comes hot on the heels of an alert from BEAMA that demand was likely to outstrip supply for some period of time.
The manufacturer’s trade association said a dramatic reduction in global steel production in the early days of the 2020/2021 pandemic had led to severe shortages. It added that, since mid-2020, the call for the types of steel used in cable management products, along with other applications, has increased as businesses attempt to meet a growth in demand and complete unfinished projects.
[edit] Comments
Both organisations are urging any members who are experiencing issues or want to find out more, to get in touch. ECA and SELECT are committed to offering advice and finding solutions to help members overcome obstacles created by these unprecedented times.
ECA’s CEO, Steve Bratt said: “When planning a project, bear in mind the world has changed. Delays in availability of some materials are impacting on cost and completion time. Our advice is to order the materials you need in good time to ensure you can finish as planned.”
Alan Wilson, managing director of SELECT, said: “Shortage of materials is an issue that will affect all contractors, so it’s vital for everyone to plan ahead and take proactive measures now.
“We join ECA in urging all members to keep abreast of any updates and recognise that this could well be an issue as the year develops. Ordering well in advance and factoring in for potential shortages and rising costs will help if there is any ongoing disruption to the supply chain.”
This article originally appeared under the headline, 'Materials shortage - ECA and SELECT warn Members to plan ahead'. It was published on 10 May 2021.
--ECA
[edit] Related articles on Designing Buildings Wiki
- Articles by the Electrical Contractors' Association (ECA).
- BEAMA.
- Careful planning required during cable management materials shortages.
- CLC urges inclusion of fluctuations provisions in contracts.
- June 2021 construction product availability statement.
- Q2 2021 trends indicate higher costs, lower employment.
- SELECT Scotland's Electrical Trade Association.
- Shortages of cable management products.
- Steel.
- Supply chains in construction.
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Comments
Material Shortages Are Your Responsibility!
A common question asked by Specialist Contractors is: “Do material shortages and extended delivery periods entitle me to claim for an extension of time on the basis that this was unforeseen circumstances outside of our control?"
The short answer is no, it probably doesn't!
Extension of Time Explained
Most construction subcontracts allow the construction period to be extended where there are delays that are not the Specialist Contractor's fault due to matters set out in the contract. This is described as an extension of time. Commonly abbreviated to EOT.
Not all Sub-Contracts are the same, and you need to be particularly careful when it comes to contracts drafted by the Contractor, or if the Contractor has heavily amended a standard form contract.
Crucially, even in a Standard Form JCT contract there is no provision for extension of time due to inability to obtain materials!
Is There A Way You Can Avoid The Consequences?
If you delay the Contractor, you become liable for a big thick sandwich of costs.
These are:
• Liquidated Damages (if the delay results in the Contractor incurring them)
• The Contractor's own costs
• Any other Subcontractor's cost (if delayed by your delay)
So, it's imperative that you look carefully to see if there are other arguments to run, such as "force majeure".
One things for sure, and that's it isn't straightforward, because when it comes to risk and money, Employers and Contractors like to pass the former down the supply chain and hang on to the latter!
More information is available at: https://www.streetwisesubbie.com/